PHASE 4: Oct 2012 – Sep 2013
a. Camping Area 3 – Break ground for Camping Area 3. The area chosen is in a flat meadow close to the stream on the south side. This campsite will have a central fire pit.
b. Chalets & Mattresses- Construct 5 chalets that will accommodate 6-8 campers each. Estimated cost: $ 3,800/chalet ($19,000 total)
c. Tonga Kitchen – Erect a “Tonga kitchen” near the center of Camping Area 3. Estimated cost: $ 2,000
d. Challenge Course- Develop a challenge/obstacle course for groups of campers. Such a course will help develop team-work and trust amongst participants. Estimated cost: $ 2,000
e. Pit Latrine-- Dig pit latrine and then erect a latrine shelter that also has a plumbed hand washing station. This facility will have 4 toilet seats. Estimated cost: $ 1,450
f. Nsaka #3 -- Build a brand new nsaka #3 overlooking agriculture area below citrus orchard. A third nsaka will allow 3 churches to meet simultaneously, break out sessions, or men and women from a church to meet separately. Estimated cost: $ 10,000
g. Agricultural/Gardening- Complete development of the agricultural and gardening areas used by national workers and for Income Generation Training. Estimated cost: $ 2,000
TOTAL ESTIMATED COST FOR PHASE 2: $ 36,450